Looking at the schedule

Date Event
July 2016 Pre-filing process begins
August 2016 Open Season
August 2016 Open Houses
October 2016 File Draft Resource Reports
November 2016 FERC Scoping Sessions
January 2017 Submit 7(c) Application
November 2017* Requested Date for FERC Final Order
December 2017* FERC Notice to Proceed
February 2018* Anticipated Construction Start
November 2018* Target In-Service Date

*Anticipated schedule and dates based on receiving necessary approvals