We’re committed to protecting the environment and an open process that provides the opportunity for all voices to be heard.
As an interstate project, the Spire STL Pipeline was reviewed for siting and permitting by the Federal Energy Regulatory Commission (FERC). The FERC was the lead agency for other federal and state, and local permitting authorities. The pipeline is wholly owned and operated by Spire STL Pipeline LLC. Information regarding our regulatory filings is available under Docket No. CP17-40 in FERC’s eLibrary website here.
On August 3, 2018, the Federal Energy and Regulatory Commission approved a Certificate of Public Convenience and Necessity for the Spire STL Pipeline. This approval gave a path forward for the project, and as of November 2019, there's another source of energy to warm homes, fuel businesses and move communities forward.
Explore our filings below.
To review the Spire STL Pipeline Amendment to Certificate Application, click here.
To review the Spire STL Pipeline Notice of Amendment, click here.
Appendix 1-B Alignment Sheets (1)
Appendix 1-B Alignment Sheets (2)
Appendix 1-B Alignment Sheets (3)
Appendix 1-B Alignment Sheets (4) Part 1
Appendix 1-B Alignment Sheets (4) Part 2
Appendix 1-B Alignment Sheets (5) Part 1
Appendix 1-B Alignment Sheets (5) Part 2
Appendix 1-B Alignment Sheets (6) Part 1
Appendix 1-B Alignment Sheets (6) Part 2
Appendix 1-B Alignment Sheets (7)
Appendix 1-B Alignment Sheets (8) Part 1
Appendix 1-B Alignment Sheets (8) Part 2
Appendix 1-B Alignment Sheets (9)
Appendix 1-B Alignment Sheets (10)
Appendix 1-B Alignment Sheets NCE (1)
Appendix 1-B Alignment Sheets NCE (2)
Appendix 1-B Chain of Rocks Site Layout
Appendix 1-C - Army Corps of Engineers
Appendix 1-C - Illinois Department of Natural Resources
Appendix 1-C - MO Department of Natural Resources
Appendix 1-C - Local Agents & Governments
Draft Resource Report 1 Appendix 1A
Spire STL Pipeline Certificate Application - January 2017
Appendix 1-B Alignment Sheets - January 2017
Appendix 1-B Alignment Sheets (2) - January 2017
Appendix 1-B Alignment Sheets (3) - January 2017
Appendix 1-B Alignment Sheets (4) - January 2017
Appendix 1-B Alignment Sheets (5) - January 2017
Appendix 1-C (1) - January 2017
Appendix 1-C (2) - January 2017
Appendix 1-C (3) - January 2017
Appendix 1-C (4) - January 2017
Appendix 1-C (5) - January 2017
Appendix 1-C (6) - January 2017
Resource Report 1 - January 2017
Resource Report 1 - April 2017
Appendix 1-A Topographic Maps - April 2017
Appendix 1-A Topographic Maps (2) - April 2017
Appendix 1-B Alignment Sheets (1) - April 2017
Appendix 1-B Alignment Sheets (2) - April 2017
Appendix 1-B Alignment Sheets (3) - April 2017
Appendix 1-B Alignment Sheets (4) - April 2017
Appendix 1-B Alignment Sheets (5) - April 2017
Appendix 1-B Alignment Sheets (6) - April 2017
Appendix 1-B Alignment Sheets (7) - April 2017
Appendix 1-B Alignment Sheets (8) - April 2017
Appendix 1-B Alignment Sheet Index-North County - April 2017
Resource Report 2 - January 2017
Resource Report 3 - January 2017
Resource Report 4 - January 2017
Resource Report 5 - January 2017
Resource Report 6 - January 2017
Resource Report 7 - January 2017
Resource Report 8 - January 2017
Resource Report 9 - January 2017
Draft Resource Report 7 Appendix A1
Implementation plan - Attachment B
Implementation plan - Attachment C - Construction Alignment Sheet 1
Implementation plan - Attachment C - Construction Alignment Sheet 2
Implementation plan - Attachment C - Construction Alignment Sheet 3
Implementation plan - Attachment C - Construction Alignment Sheet 4
Implementation plan - Attachment C - Construction Alignment Sheet 5
Implementation plan - Attachment E
Implementation plan - Attachment F
Implementation plan - Attachment G
Implementation plan - Attachment H
Implementation plan - Attachment I
Implementation plan - Attachment J
Implementation plan - Attachment K
Implementation plan - Attachment L - Cold Water Creek
Implementation plan - Attachment L - Spanish Lake
Implementation plan - Attachment N
Implementation plan - Attachment R